Progress billing

What does progress billing mean?

Invoicing a long job in stages as the work is completed, rather than once at the end.

On this page

In practice

Progress billing keeps cash moving on jobs that run for weeks or months. The schedule of values is agreed up front (mobilisation, rough-in, finish), and each draw invoices the percentage complete, minus retainage. Every draw is a real invoice with its own number and its own due date.

What is progress billing?

Progress billing is a way to invoice for work as a project moves forward instead of waiting to bill the whole job at the end. You and the customer agree on project lines and billing points, then each progress invoice requests payment for completed work, minus amounts already billed and any retainage.

It is also called construction progress billing or billing by draw. A draw is one request for payment during the job. The contract should explain what work each draw covers and how you measure completion.

How do you calculate a progress billing draw?

A schedule of values assigns a dollar value to each part of the job; its total should match the contract price. For each line, multiply the value by the percent complete to get work completed to date. Add the lines, subtract previous billings, then subtract retainage withheld from this draw. The result is the amount due.

For a $48,000 kitchen remodel at its second draw, demolition and rough-in are complete, cabinets and counters are 50% complete, and finish has not started. Work completed totals $26,000. With $16,000 billed previously, this draw's work is $10,000. Retain 10%, or $1,000, and request $9,000.

Agree on how you measure percent complete before work starts. Base it on the portion actually completed, not time passed. See how retainage affects billing.

When should a small contractor use progress billing?

Consider it when a job lasts long enough that carrying labor and material costs until the final invoice would pressure your cash. It can suit jobs with clear phases or large material purchases. You request payment as agreed portions of the work are completed.

For a short service call or small job you can finish at once, the paperwork for each draw may not be worthwhile. Before accepting a longer job, agree in writing on the contract amount, draw dates or milestones, completion method, retainage, and invoice approval. Document how scope changes affect the values.

Payment timing and construction contract rules vary by state, so check your state. Read about contractor payment schedules. If the customer requires an industry form, confirm it before the first draw. AIA billing is one format you may be asked to prepare.

What goes on a progress invoice?

Make the invoice easy to compare with the contract and prior draw. Include your business and customer details, invoice number and date, project identifier, contract amount, draw number or billing period, payment terms, and a description of the work.

For each schedule-of-values line, show its original value, percent complete to date, earned amount, previous billings, and amount due this draw. List retainage and its calculation separately. Show approved changes as separate lines and attach the backup the customer requests.

State the current amount due and how to pay. Carry billed-to-date figures forward to the next draw. Ask whether a draw request means a specific form or approval process, and whether payment paperwork needs a lien waiver. Bill an upfront materials charge separately with a deposit invoice and show how it is credited later.

Second draw on a $48,000 kitchen remodel
Schedule of values lineScheduled valueComplete at second drawWork completed to dateBilling calculation
Demolition$4,000100%$4,000
Rough-in$12,000100%$12,000
Cabinets and counters$20,00050%$10,000
Finish$12,0000%$0
Total scheduled values and completed work$48,000$26,000
Previous billings$16,000
This draw's work: $26,000 completed to date minus $16,000 previously billed$10,000
Retainage: $10,000 x 10%$1,000
Amount due: $10,000 less $1,000 retainage$9,000

Questions

How does progress billing work in construction?

You and the customer agree on job values and billing points, then track work completed at each draw. Multiply each line's value by its percent complete, total the earned work, subtract earlier billings, and deduct retainage for this draw. Send the resulting progress invoice with the backup the customer requested.

What is the difference between a progress invoice and a draw request?

Both can mean a request for payment during a project. A progress invoice typically shows completed work and the amount due; a draw request may refer to the customer's required package or approval step. Ask what form, backup, and sign-offs the customer expects, and check your contract wording.

Should I subtract retainage from every progress billing?

Follow the retainage terms agreed with the customer, and show the amount separately. In the example, retainage is 10% of $10,000 in new work, or $1,000, leaving $9,000 due. Retainage rules can vary by state, so check your state.

What should I put on a construction progress invoice?

Identify the project and draw, then show each scheduled line's value, completion percentage, earned amount to date, previous billings, retainage, and amount due. Include the contract reference, invoice date and number, payment terms, and required backup. Ask about approval steps before submitting the first invoice.

About this page

Invocket Editorial

Written by the team that builds Invocket, an invoicing app for contractors. We check prices and rules against published sources, name them on the page, and update the page when they change. How we write and check these pages.