In this chapter
Choosing terms you can enforce, taking deposits that cover materials, and billing long jobs in stages.
On this page
Payment terms decide how long you carry the cost of a job before the customer pays. For one-off residential work, use due on receipt; for office-paid customers, agree on Net 15 or Net 30. Take a deposit within your state’s limits, bill long jobs in stages, and review billed, paid, outstanding, and overdue amounts each month. Put the terms on the estimate before work starts.
Terms are part of the price
A $4,000 job is not the same deal under every payment date. When you buy materials and pay labor before collection, you carry those costs until the customer pays.
Say you put $1,600 of materials on a card at 24% APR for 40 days. Simple interest is $1,600 × 0.24 × 40 ÷ 365 = $42.08, before other costs or card terms.
Account for payment timing in your price. A long wait ties up cash for the next job’s materials or payroll. Price for that cost, ask for an allowed deposit or stage payment, or agree on shorter terms before sending the estimate. Put the due date on the estimate and repeat it on the invoice. Revise the estimate if the customer requests different terms, and get agreement before work starts. The payment terms definition covers the basic language.
Which terms to use
Match terms to the customer’s payment process and how much work you have completed. For details, see this comparison of Net 30 and due on receipt.
| Term | Good fit | What to write or confirm |
|---|---|---|
| Due on receipt | One-off residential work where the customer pays directly | State when the invoice is delivered and how the customer can pay. |
| Net 15 | Repeat residential customers or a small commercial account paid by an office | Confirm the invoice reaches the person who approves it, and state the due date. |
| Net 30 | Property managers, general contractors, and businesses with an accounts-payable process | Ask about required forms, invoice submission steps, and approval timing before accepting the term. |
| 2/10 Net 30 | A customer who can pay early, when the discount is worth the cost to you | State the discount and qualifying payment window clearly, then check the arithmetic below. |
Before accepting office-paid work, ask who receives the invoice and whether they need a purchase order, job number, or signed completion ticket. Send it through their approval process.
Deposits
Size a deposit around costs you must commit before the first customer payment, such as special-order materials, delivery, or a scheduled first day of labor. Check the rules for your state and type of work before putting an amount on the estimate. Do not assume a familiar percentage is allowed everywhere.
California’s Contractors State License Board says, “The down payment cannot be more than $1,000 or 10 percent of the contract price, whichever is less, for a home improvement job or swimming pool.” Maryland Code, Business Regulation 8-617, and the Maryland Home Improvement Commission say a home improvement contractor may not receive a deposit of more than one-third of the contract price at or before signing. Massachusetts General Laws chapter 142A, section 2, says an advance deposit may not exceed the greater of one-third of the total contract price or the actual cost of special-order or custom materials that must be ordered in advance. See the guide to how much deposit to ask for before setting your process.
Record the deposit as a payment against the job, then subtract it from the balance invoice. A deposit invoice gives that payment its own record.
Progress billing on long jobs
On a multiweek job, agree on billing stages before work begins. Progress billing means invoicing as defined portions of work are completed.
Start with a schedule of values, a list of priced job parts such as demolition, rough-in, and finish work. Its values should add up to the contract amount. If a $3,000 rough-in line is half complete, the bill for it is $1,500 before retainage or prior billing adjustments.
Choose inspectable milestones, such as a completed rough-in. State the stage, completion requirement, amount, and due date. Retainage is an amount held back until a later condition is met. State its amount and release condition, and track it separately from unpaid invoices. See the contractor payment schedule guide.
Early-payment discounts: the real cost
With 2/10 Net 30, the customer takes 2% off by paying within 10 days; otherwise, the full invoice is due in 30 days. You give up 2% to collect 20 days sooner. Annualized cost: 2 ÷ 98 × 365 ÷ 20 = 0.3724, or about 37.2% a year. The 98 is the amount collected after discount on a 100% invoice.
On a $1,000 invoice, the discount is $20: you collect $980 early instead of $1,000 later. Offer it only if early cash solves a real timing problem. Put the discount and payment window on the accepted estimate or contract and invoice. See the early payment discount definition.
A four-week cash flow forecast
Start with available cash, add expected weekly receipts, and list bills and payroll when due. Update the forecast when a customer delays approval or a supplier changes a delivery date.
A small remodeler starts with $6,200 and expects a $2,500 deposit in week 1, a $4,000 progress payment in week 2, and a $3,100 final payment in week 3. Materials cost $2,800 in week 1, payroll is $1,900 each week, and truck and insurance cost $650 in week 4.
| Week | Starting cash | Money in | Money out | Ending cash |
|---|---|---|---|---|
| 1 | $6,200 | $2,500 deposit | $2,800 materials + $1,900 payroll = $4,700 | $4,000 |
| 2 | $4,000 | $4,000 progress | $1,900 payroll | $6,100 |
| 3 | $6,100 | $3,100 final | $1,900 payroll | $7,300 |
| 4 | $7,300 | $0 | $1,900 payroll + $650 truck and insurance = $2,550 | $4,750 |
Each ending balance equals starting cash plus money in minus money out. This plan stays above zero, with a low of $4,000 in week 1. If a customer delays a deposit or progress payment, move that receipt to the expected week and recalculate. A payment arriving after payroll cannot cover that payroll.
List expected receipts by customer and invoice, and outflows by supplier, payroll date, and bill. Mark uncertain receipts. If a week shows a shortfall, follow up on the invoice, discuss an allowed stage payment before the next stage, or move a purchase date if the contract allows it.
The four numbers to watch, and DSO
Review four totals each month: billed, paid, outstanding, and overdue. Billed is what you invoiced in the period. Paid is what you actually collected. Outstanding is the unpaid balance, including amounts not yet past due. Overdue is the part that has passed its stated due date.
If billed grows while paid stays flat, more cash is tied up in customer balances. If overdue is growing, check whether invoices reached the right person and ask for an approval or payment date.
Days sales outstanding (DSO) estimates the average time to collect after a sale. Compare it with your past periods. A rising DSO can flag slower collection; review aged balances to find the delayed invoices. Use this guide to get paid faster for follow-up steps.
When cash is tight
Find the first projected shortfall in your four-week forecast. Trace it to the invoice, purchase, or payroll date creating it.
- Set a larger deposit only when the law and contract allow it. Tie it to the costs you must commit before work begins, and verify the applicable state rule first.
- Use shorter terms on new jobs. Agree on the due date before accepting the work, especially when the customer has not built a payment history with you.
- Bill in stages on longer work. Set milestones and amounts in advance, and pause before the next stage if a required payment has not arrived, consistent with the contract.
- Ask about invoice factoring. With invoice factoring, a business sells or assigns an eligible invoice to a finance company for funding, subject to that provider’s terms. Read the agreement closely, including fees, recourse, customer notification, and what happens if the customer disputes the invoice. Compare the full cost and obligations with the cash timing problem you are trying to solve.
- Consider a line of credit. It may help cover a timing gap, but review the lender’s rate, fees, repayment rules, and collateral terms before relying on it. Do not count available credit as collected customer revenue.
If a customer cannot meet the schedule, agree on revised dates and amounts in writing before continuing or committing more costs. See the cash flow definition to distinguish timing from profit.
FAQ
Should contractors put payment terms on the estimate or invoice?
Put them on the estimate or contract before work starts. Repeat them on each invoice, and document any agreed change.
Can I ask for a deposit on every job?
Check the state and contract rules before setting a standard. When allowed, base the deposit on costs you commit early and credit it against the job total.
When should I switch to progress billing?
Consider it when a job lasts long enough that you would otherwise carry substantial materials or labor costs until completion. Agree on stages, values, evidence of completion, due dates, and any retainage before starting. Use milestones both sides can identify, rather than a subjective description of progress.
Is a 2% early-payment discount worth offering?
It depends on whether earlier collection solves a real cash need and whether the discount costs less than your alternative. For 2/10 Net 30, the annualized cost is about 37.2% using the calculation in this guide. Compare that cost with the value of receiving the payment sooner before offering it.
What should I do if a customer is late?
Check that the invoice reached the right person and includes the documents the customer needs to approve it. Ask for a specific payment date and record the response. Update your cash forecast if the expected receipt moves, then review the contract before changing work or payment stages.

About this page
Invocket Editorial
Written by the team that builds Invocket, an invoicing app for contractors. We check prices and rules against published sources, name them on the page, and update the page when they change. How we write and check these pages.