What does retainage mean?
A percentage of each payment the client holds back until the job is finished and accepted.
On this page
In practice
Retainage (retention) is typically 5–10% and is common in construction. It is money you have earned but cannot collect yet, so it belongs on your statement as outstanding, not as paid. Many states cap the percentage and set a deadline for release, the contract should say when the final retainage invoice can be issued.
How retainage works
Retainage (also called retention) is a percentage of each progress payment that the owner or general contractor holds back until the job is finished. It gives the payer a cushion against unfinished work, defects, and unpaid subs. It is money you have earned but will not see until the end of the project.
Typical retainage is 5% to 10% of each payment. On a progress bill of $20,000 with 10% retainage, the client pays $18,000 and holds $2,000. Over the life of the job the held amounts add up, and on a $60,000 job at 10%, that is $6,000 sitting in someone else's account.
Retainage only applies if it is in the contract. If you are a sub, the general contractor will usually pass down the same percentage the owner holds from them.
When retainage is released
Most contracts release retainage in one of these ways:
- At final completion, after the punch list is done and accepted.
- At substantial completion, with a smaller amount held back for open punch items.
- Reduced partway through, for example dropping from 10% to 5%, or stopping new retainage once the job is 50% complete.
The owner usually wants paperwork before releasing it: a final invoice, a final lien waiver (send a conditional one with the invoice), warranties, manuals, and sometimes lien waivers from your suppliers and subs.
State retainage and prompt payment laws
Many states have laws that limit how much retainage can be held, set deadlines for releasing it after completion, or charge interest when it is paid late. Some rules apply only to public projects, some also cover private work, and the percentages and deadlines differ from state to state. Some states require retainage on certain projects to be held in a separate or escrow account.
Because the rules vary so much, check your state's prompt payment and retainage statutes before you sign a contract that holds retainage, and before you chase a late release. A contract clause that conflicts with state law may not be enforceable.
Negotiating retainage before you sign
Retainage terms are usually set in the contract, and they are easier to change before you sign than after. Things worth asking for:
- A lower rate, such as 5% instead of 10%, especially on small jobs where the owner's risk is limited.
- A reduction or stop once the job is 50% complete.
- Release within a fixed number of days after substantial completion, not "at the owner's discretion."
- Partial release for your portion of the work if you are a sub who finishes early, so you are not waiting for the whole building.
- No retainage on stored materials or on change order work billed at completion.
Invoicing retainage correctly
Show retainage on every progress invoice so there is never an argument about how much is being held. Each invoice should list the total work completed to date, retainage held to date, previous payments, and the amount due this period. A construction invoice template with a retainage line makes this routine.
At the end, send a separate retainage release invoice for the total amount held. Keep retainage visible on your aging report as its own category, because it can sit unpaid for months and it is easy to forget. Build it into your cash flow planning too: if 10% of every job arrives 30 to 90 days after the job ends, you need enough cash to cover your costs in the meantime.
| Invoice | Work billed | Retainage held (10%) | Paid to you |
|---|---|---|---|
| Progress bill 1 | $20,000 | $2,000 | $18,000 |
| Progress bill 2 | $25,000 | $2,500 | $22,500 |
| Progress bill 3 | $15,000 | $1,500 | $13,500 |
| Retainage release | -$6,000 released | $6,000 | |
| Total | $60,000 | $0 still held | $60,000 |
Questions
What is a typical retainage percentage?
Most contracts use 5% or 10% of each progress payment. Some reduce it to 5% or stop withholding once the project is half complete. Some states cap the percentage, especially on public work, so check your state's rules and your contract before agreeing to a number.
Is retainage the same as a retainer?
No. Retainage is money the client holds back from your payments until the job is finished. A retainer is money the client pays you up front before work begins. One protects the client, the other protects you.
How do I record retainage in my books?
Retainage you have billed but not received is still money owed to you, so it is usually tracked as retainage receivable, separate from regular accounts receivable. That keeps it from being mistaken for a late payment and reminds you to invoice for it when the job closes. Ask your accountant how to handle it for your accounting method.