What does change order mean?

A written, priced amendment to an approved estimate or contract.

On this page

In practice

The scope changed, so the price changes. A change order records what was added or removed, what it costs, and the client's approval, signed before the extra work happens. Verbal change orders are the single most common reason a trades business ends up eating the difference.

How a change order works

A change order is a written, signed amendment to a construction contract that changes the work, the price, the schedule, or all three. It is how you add a bathroom fan the client decides they want, delete trim they no longer need, or charge for rotten subfloor you found after demo.

The basic flow: something changes, you describe it and price it, the client signs, and only then you do the work. The signed change order becomes part of the contract, and its amount gets added to (or subtracted from) the contract sum on your next invoice.

The rule that saves the most money is simple: no signature, no extra work. Verbal agreements on a job site are easy to make and easy to forget, and "I thought that was included" is hard to argue with when nothing is in writing. A text message with a photo and a price, answered with "yes, go ahead," is better than nothing, but a signed form is better still.

What goes on a change order form

Whether you use a change order template or write your own, these are the fields that matter:

  1. Change order number, sequential per job (CO #1, CO #2).
  2. Date the change order is issued.
  3. Project name and job address.
  4. Client name and your business name, license number if your state requires it.
  5. Original contract reference: contract date or number.
  6. Description of the change: specific, with locations, materials, and quantities.
  7. Reason: client request, hidden condition, code requirement, design change.
  8. Cost breakdown: labor, materials, equipment, subcontractors, and your markup.
  9. Amount of this change, marked as an add or a deduct.
  10. Contract sum before this change, including earlier change orders.
  11. Revised contract sum.
  12. Schedule impact in days and the revised completion date.
  13. Payment terms for the change: due now, added to the next progress bill, or due at completion.
  14. Signatures and dates for both parties.

Pricing a change order

Price change orders the same way you price the original estimate: cost of labor and materials, plus overhead and profit. Many contractors charge a slightly higher markup on changes because they disrupt the schedule, require extra trips, and often involve small material orders at retail prices.

Do not forget the costs that are easy to miss: time to reorder, restocking fees for returned materials, extra dump runs, a second inspection, and the days the change adds to the job. If a change pushes the completion date, write that on the form so a late finish is not blamed on you.

Deducts work the same way in reverse. If the client drops $1,000 of crown molding you already bought, the credit should be net of what you cannot return.

Change orders on invoices

List each approved change order as its own line on your progress or final invoice, with its number, so the client can match every dollar to a signature. On a schedule of values, approved changes are added as new lines at the bottom rather than folded into existing ones. Keep unapproved changes off the invoice until they are signed, and note any pending ones on your lien waivers so you do not waive them by accident.

Change order log on a $32,000 basement finish
ItemDescriptionAdd / deductContract sum
Original contractBasement finish per signed proposal$32,000
CO #1Add 6 outlets and a dedicated circuit for a home office+$1,450$33,450
CO #2Delete crown molding in family room (materials returned)-$800$32,650
CO #3Upgrade bathroom floor tile, client selection+$2,275$34,925
Revised contractOriginal plus approved change orders+$2,925 net$34,925

Questions

Who signs a change order?

Both parties to the contract: you and the client or owner, or you and the general contractor if you are a sub. On larger jobs an architect may also sign. Make sure the person signing has authority to approve extra cost, not just a site supervisor or the owner's relative.

What if the client refuses to sign a change order?

Do not do the extra work until the dispute is settled. If the change is required to finish the job, such as a code correction, put your position in writing, document the condition with photos, and check what your contract says about disputed changes. Many contracts require you to keep working and resolve the price later.

Is a change order the same as a change order request?

No. A change order request, sometimes called a proposed change order, is your priced proposal for a change. It becomes a change order once both parties sign it. Until then, it is only an offer and does not change the contract sum.

About this page

Invocket Editorial

Written by the team that builds Invocket, an invoicing app for contractors. We check prices and rules against published sources, name them on the page, and update the page when they change. How we write and check these pages.