Lien waiver

What does lien waiver mean?

A document in which a contractor gives up the right to place a mechanic's lien, usually in exchange for payment.

On this page

In practice

Waivers come in four flavours: conditional or unconditional, partial or final. A conditional waiver only takes effect once the payment clears, which is the one you want to sign when a cheque is still in the post. Several states publish statutory wording that must be used exactly.

What a lien waiver does

A lien waiver is a signed document in which you give up some or all of your right to file a mechanics lien on a property, usually in exchange for payment. Owners, general contractors, and lenders ask for them so they know the people who worked on the job have been paid and will not put a claim on the title later.

For a one-person contractor, the lien waiver is the other half of every payment. The client wants the waiver, you want the check, and the order in which those two things happen is where the risk sits.

Conditional vs unconditional

A conditional waiver only takes effect once you actually receive the payment it describes. If the check bounces or the wire never arrives, the waiver has no effect and your lien rights stay intact. This is the one you can safely send with an invoice or pay application.

An unconditional waiver takes effect as soon as you sign it, whether or not you have been paid. Sign an unconditional waiver only after the funds have cleared your account. Signing one in advance, in exchange for a promise to pay, is one of the most common ways small contractors lose their bargaining power.

Progress vs final, and the four common types

A progress (partial) waiver covers work through a specific date or a specific payment. You keep lien rights for work after that date and for any amount not covered, such as retainage. A final waiver covers the whole job and gives up all remaining lien rights. Use it only at the end, for the last payment.

Combine the two choices and you get the four standard forms:

  1. Conditional waiver on progress payment: sent with a progress invoice; effective when that payment clears.
  2. Unconditional waiver on progress payment: sent after a progress payment clears; covers work through the stated date.
  3. Conditional waiver on final payment: sent with the final invoice; effective when final payment clears.
  4. Unconditional waiver on final payment: sent after final payment clears; ends your lien rights on the job.

Lien waiver forms and state rules

Lien law is state law, and the rules vary more than most contractors expect. About a dozen states publish statutory lien waiver forms, and in most of them a waiver has to follow the statutory wording closely to be valid. States with statutory forms include Arizona, California, Georgia, Massachusetts, Michigan, Mississippi, Missouri (for residential work), Nevada, Texas, Utah, and Wyoming. Florida has a statutory form but does not require you to use it.

In states without a statutory form, the parties can use any form, which means the wording is whatever the owner or general contractor hands you. Read it before signing. Watch for:

  • A "conditional" form that says "unconditional" anywhere in the body.
  • A "through date" later than the work you are being paid for.
  • Language that waives claims beyond lien rights, such as all claims for extra work or pending change orders.
  • An amount that does not match the payment.

Check your state's statute or ask a local construction attorney which form applies to your projects.

A simple waiver routine

Send a conditional progress waiver with each progress invoice. When the payment clears, send the matching unconditional progress waiver. At the end, send a conditional final waiver with the final invoice and the unconditional final waiver once the last payment, including retainage, is in your account. Keep a copy of every waiver with the invoice it matches, and note unpaid change orders on each one so they are not swept in by accident.

The four common lien waiver types
TypeWhen you send itWhat it gives upRisk to you
Conditional, progressWith a progress invoiceLien rights for that payment, once paidLow
Unconditional, progressAfter the progress payment clearsLien rights for work through the stated dateLow if paid; high if signed before payment
Conditional, finalWith the final invoiceAll lien rights on the job, once paidLow
Unconditional, finalAfter final payment clearsAll lien rights on the job, immediatelyHighest; sign only after funds clear

Questions

What is a lien waiver form?

It is the document you sign to give up lien rights on a property, either for one payment or for the whole job. In states with statutory forms, the wording is set by law and must be followed closely. In other states, the form is usually supplied by the owner, general contractor, or lender.

Should I sign a lien waiver before I get paid?

Only a conditional one. A conditional waiver takes effect when the payment clears, so it protects you if the check bounces. An unconditional waiver takes effect when signed, so signing it before you have the money means giving up your lien rights for a promise.

Does a lien waiver waive my right to be paid?

It waives your right to file a lien for the amounts it covers, not necessarily your right to collect a debt. But broad wording can also release claims for extra work or disputed amounts. Read the form, list unpaid change orders or retainage as exceptions, and check your state's rules.

About this page

Invocket Editorial

Written by the team that builds Invocket, an invoicing app for contractors. We check prices and rules against published sources, name them on the page, and update the page when they change. How we write and check these pages.

Keep going

Bill the job before you leave the driveway

No account to create, nothing to set up. Open the app and write the first estimate.

Get Invocket for iPhone