Schedule of values

What does schedule of values mean?

A breakdown of a contract price into line items that can be billed as they are completed.

On this page

In practice

Agreed before work starts on longer jobs, it turns one large contract sum into a sequence of billable milestones, mobilisation, rough-in, finish. Each progress invoice bills the percentage complete of specific lines, which is what makes a draw request checkable.

What a schedule of values is

A schedule of values (SOV) is a list that breaks the total contract price into line items, each with a dollar value. The line items add up exactly to the contract sum. Once the owner approves it, the SOV becomes the basis for every progress bill on the job: each month or at each milestone, you bill the percentage of each line that is complete.

It is standard on commercial jobs and on any project with a lender, because the bank wants to release money in proportion to the work in place. It is also useful on larger residential remodels, where it turns "how much do we owe you now?" into a simple table.

How to build one

  1. Start from your estimate. Group costs into phases or trades the owner can see and verify: demolition, framing, rough plumbing, rough electrical, drywall, cabinets, finishes.
  2. Spread overhead and profit across the lines instead of showing them as a separate item. Owners and lenders often push back on a big "overhead and profit" line that gets billed up front.
  3. Keep lines small enough to measure. A single $40,000 "interior" line is hard to agree on. Five $8,000 lines are easier.
  4. Consider separating materials and labor on big-ticket items, so you can bill for materials delivered and stored on site if the contract allows it.
  5. Make it add up to the contract sum to the dollar.

Front-loading, and why it backfires

Front-loading means putting more value on early lines (mobilization, demo, rough-in) than they are worth, so you collect cash sooner. It is tempting for a one-person business with thin cash reserves. But owners, architects, and lenders review SOVs for exactly this, and an obviously front-loaded schedule can get rejected or make every later pay request harder to approve.

If you need cash early, the cleaner options are a deposit written into the contract, or billing for stored materials once they are delivered.

A balanced schedule also protects you. If the job stops halfway, because the owner runs out of money or you part ways, the SOV is the record of what you earned. Lines that reflect real costs make that number hard to dispute.

Billing against the SOV

Each billing period you report, for each line: the scheduled value, the work completed in earlier periods, the work completed this period, materials stored, the total to date, the percentage complete, and the balance to finish. Subtract retainage if the contract has it, subtract what has already been paid, and the result is the amount due.

Approved change orders are added as new lines at the bottom with their own values, which keeps the original schedule intact and makes every change easy to trace. On projects that use the AIA forms, the SOV lives on the G703 continuation sheet; see AIA billing for how that works.

In the example below, the owner has approved a $60,000 SOV. After the second billing period, $20,500 of work is complete. With 10% retainage, $2,050 is held back and $18,450 has been earned; subtract the payments already received and you have this period's amount due.

Schedule of values on a $60,000 remodel, after billing period 2
Line itemScheduled value% completeEarned to date
Demolition and haul-off$4,000100%$4,000
Framing and structural$9,000100%$9,000
Plumbing and electrical rough-in$15,00050%$7,500
Drywall, trim, and paint$14,0000%$0
Cabinets and countertops$18,0000%$0
Total$60,00034.2%$20,500

Questions

Who prepares the schedule of values?

The contractor prepares it, usually right after the contract is signed and before the first pay request. The owner, architect, or lender reviews and approves it. Once approved, it generally stays fixed, and changes are handled by adding change order lines rather than rewriting existing values.

Is a schedule of values the same as an estimate?

No. An estimate is how you arrive at the price, with detailed costs you usually keep private. A schedule of values is how you bill against that price, broken into lines the owner can check on site. Your estimate feeds the SOV, but the SOV spreads overhead and profit across lines.

Can I bill for materials not yet installed?

Often yes, if the contract allows billing for stored materials. You typically need to show that the materials are delivered, stored safely on site or in an approved location, and insured, and you may need invoices as proof. Check your contract before you bill for them.

About this page

Invocket Editorial

Written by the team that builds Invocket, an invoicing app for contractors. We check prices and rules against published sources, name them on the page, and update the page when they change. How we write and check these pages.