What does aIA billing mean?
A progress billing method that uses the AIA G702 Application and Certificate for Payment and G703 Continuation Sheet to request payment against a schedule of values.
On this page
In practice
AIA billing is the standard way to request progress payments on many commercial and lender-financed construction projects in the US. The contractor fills out two forms published by the American Institute of Architects: the G702 Application and Certificate for Payment, a one-page summary of the contract sum, work completed, retainage, and amount due, and the G703 Continuation Sheet, which lists each line of the schedule of values with work completed to date. The architect or owner reviews the application, certifies the amount, and the owner pays it. The forms are copyrighted and sold by AIA Contract Documents.
How AIA billing works
AIA billing is a form of progress billing built around two documents from the American Institute of Architects: the G702 Application and Certificate for Payment and the G703 Continuation Sheet. Together they are often called a pay application, or pay app. Owners, architects, and lenders like them because every application follows the same structure, so the math can be checked quickly.
The cycle usually looks like this:
- Before the first billing, you submit a schedule of values that splits the contract sum into line items. Once approved, it becomes the G703.
- Each billing period, usually monthly, you update the G703 with the work completed and materials stored for each line.
- You carry the totals to the G702, subtract retainage and previous payments, and arrive at the current payment due.
- The architect or owner's rep reviews the application against the work on site and certifies the amount, sometimes adjusting it.
- The owner pays the certified amount within the time the contract sets, often with a lien waiver exchanged for the payment.
The G703 Continuation Sheet
The G703 is where the detail lives. Each row is one line of the schedule of values, and the columns track the line from start to finish:
- Item number and description of work.
- Scheduled value: the dollar amount assigned to that line.
- Work completed from previous applications.
- Work completed this period.
- Materials presently stored: delivered but not yet installed.
- Total completed and stored to date: previous plus this period plus stored.
- Percent complete and balance to finish.
- Retainage, where it is calculated by line.
Approved change orders are added as new lines at the bottom, so the original values stay untouched.
The G702 Application and Certificate for Payment
The G702 is a one-page summary. It starts with the original contract sum, adds the net change from change orders to get the contract sum to date, then takes the total completed and stored from the G703. Retainage comes off that total, the payments already certified in earlier applications come off next, and what remains is the current payment due. It also shows the balance to finish, including retainage, and a summary of change orders.
The lower part of the form holds the contractor's signed statement that the work is billed correctly and earlier payments have been passed on, often notarized, and the architect's certificate for the amount approved.
In the example below: $55,000 completed and stored, less 10% retainage ($5,500), is $49,500 earned. Previous certificates totaled $31,500 ($35,000 of work less $3,500 retainage), so the current payment due is $18,000.
About the forms themselves
G702 and G703 are copyrighted documents sold by AIA Contract Documents, the AIA's publishing arm. You get them by buying a license or through software licensed to produce them. Free downloads that copy the official forms are not licensed. Many residential and smaller commercial clients will accept a pay application that follows the same structure on your own letterhead, but if the contract calls for actual AIA documents, use licensed ones.
For simpler jobs, a construction invoice template with lines for work to date, retainage, and previous payments covers the same information.
| Description | Scheduled value | Previous | This period | Stored | Total to date | % |
|---|---|---|---|---|---|---|
| Sitework | $12,000 | $12,000 | $0 | $0 | $12,000 | 100% |
| Framing | $30,000 | $18,000 | $12,000 | $0 | $30,000 | 100% |
| Electrical | $20,000 | $5,000 | $6,000 | $2,000 | $13,000 | 65% |
| Finishes | $38,000 | $0 | $0 | $0 | $0 | 0% |
| Total | $100,000 | $35,000 | $18,000 | $2,000 | $55,000 | 55% |
Questions
What is the difference between G702 and G703?
The G702 is the one-page summary and certificate: contract sum, change orders, total completed, retainage, previous payments, and current payment due. The G703 is the continuation sheet with a row for each line of the schedule of values. The G703 totals feed the G702, and the two are submitted together.
Can I use a free AIA G702 template?
The official G702 and G703 are copyrighted by the AIA and sold through AIA Contract Documents, so copies of the actual forms are not free to reuse. You can build your own pay application with the same kind of information. If your contract requires AIA documents, buy licensed copies or use licensed software.
How often do you submit an AIA pay application?
Usually once a month, on a date set in the contract, often with a pencil draft reviewed by the architect or owner a few days before the formal submission. Some projects bill at milestones instead. Missing the submission date can push your payment to the next cycle, so put it on your calendar.