Write a change order before work starts outside the signed scope. Describe the change, price added or deleted work, state the schedule impact, and get the customer’s written approval. Then do the work, document completion, and bill it as its own line. Both sides have a record of the change and agreed price.
When do you need a change order?
Use a change order whenever the work, materials, price, or timing differs from the approved agreement. Even a small extra can affect labor, material orders, inspections, or another trade’s start. Record the change instead of relying on a handshake or casual comment.
Common reasons include:
- Customer requests: The homeowner asks for another outlet, a larger shower niche, an extra coat of paint, or different tile.
- Hidden conditions: Demolition exposes rotten framing, a leaking valve, damaged wiring, or an uneven floor you could not see when pricing the job.
- Code-required work: An inspection or field condition calls for additional work. Describe the finding and proposed work, and check applicable requirements with the local authority or a qualified professional.
- Material substitutions: The specified product is unavailable, the customer selects a different finish, or a product change affects labor or lead time.
- Deletions: The customer removes an item, such as a mirror, cabinet, or fixture, and the contract needs a credit.
Compare the request with the signed scope of work. If it is included, explain that before calling it extra. If it is outside the agreed scope, write it down before starting. A faucet substitution, for example, could change product cost, installation time, or delivery date.
What fields belong on a change order?
Make the change order specific enough to connect to the original job and clear to someone who was not at the site. Include:
- Customer and project identification, plus the original contract or estimate number.
- Change order number and date.
- Description of added, revised, or deleted work, including useful quantities or product details.
- Price or credit, payment timing, and schedule effect.
- Customer approval and date, with a copy saved to the job record.
For the full field list and an example log, see the glossary entry for a change order. A reusable change order template or form speeds up the process, but leave room to describe the actual condition and work.
Number each change, such as CO #1 and CO #2, and use the number in the estimate, approval message, work notes, and invoice. A written schedule of values groups contract work for billing; keep each change identifiable instead of folding it into an unrelated line.
What is the change order process on the job?
- Stop the affected work. Do not cover, remove, or alter the condition further unless action is needed to protect people or property. Document urgent protective work and explain the issue to the customer.
- Photograph and measure. Take a wide photo showing location and close photos of the condition. Record quantities, dimensions, and relevant product labels.
- Describe the finding and proposed work. Separate what you observed from what you propose. “Rotten subfloor under the tub, approximately 32 sq ft exposed” is clearer than “floor problem.” Say what removal, replacement, disposal, and finish work the price includes.
- Price the change. Include labor, materials, equipment, disposal, and other costs. State assumptions. If you cannot price the full work until opening more of the assembly, define and price the next step, then pause for approval.
- State the schedule impact. Give the added workdays or explain what date depends on a delivery or customer decision. Say whether other work can continue.
- Get approval. Send the change order and get clear written acceptance before starting the extra work. Save the signed page or message.
- Complete and bill it. Track labor and materials, take an after photo when useful, and put the change on the invoice under its own number and description.
Keep approved changes with the original agreement. Invocket has no change-order document. You can write the extra as a new estimate, which gets its own EST number and can carry photos of what you found, and mark it accepted when the customer approves, so the extra has its own record. A construction estimate template can make the original scope and exclusions easier to compare with later requests.
How do you price a change order?
Price the work you expect to perform, not just the visible material. Count labor, materials, delivery or disposal, equipment, and any follow-up visit. Apply your normal pricing method. See how to price a job and the explanation of markup versus margin if you need to review your base price.
During a bathroom remodel, demolition reveals 32 sq ft of rotten subfloor. The change covers removal, new plywood, fastening, and an extra dump run. The work adds one day.
- Labor: 4 hours × $85 per hour = $340.
- Materials: 2 sheets of 3/4 in. plywood at $58 each = $116, plus $24 for fasteners and adhesive. Materials cost = $140.
- Materials markup: $140 × 20% = $28. Materials charge = $140 + $28 = $168.
- Extra dump run: $45.
Change order total: $340 + $168 + $45 = $553. Schedule impact: add 1 day. State the area and replacement included, and whether finish flooring or concealed damage beyond the exposed 32 sq ft is excluded or needs another approval.
For uncertain work, define an allowance or not-to-exceed amount only when you can explain what it covers and how added work will be approved. For time-and-materials work, state the rates, materials basis, and approval method.
How can you get approval fast?
On site, show the photos, read the work description and price aloud, then send the form for signature. If the customer is away, send a text or email with the photo, amount, schedule effect, and a direct request to approve or decline.
For example: “We found rotten subfloor under the bathroom tile, about 32 sq ft. CO #1 covers removal, replacement with 3/4 in. plywood, fasteners and adhesive, and one extra dump run. Price: $553. Add 1 day. Reply ‘I approve CO #1 for $553 and the one-day schedule change’ or sign the attached form. We will hold this work until you approve.”
Follow the approval method in your contract. It may say who can approve changes and whether a signature is required or a written reply is enough. If your contract is silent, add a line to the next one that says how changes get approved. Save the full message thread either way.
If two owners or a property manager are involved, confirm who can approve added work. Send the change order to that decision-maker and save the response. Get the written approval your contract requires before proceeding.
How do deductive change orders and credits work?
A deductive change order records removed work and its credit. Use it when a customer supplies an item, selects a less costly option, or deletes part of the scope. Describe the deleted work, show the credit as a negative amount, and update the revised contract total.
Do not assume the credit equals the item’s purchase price. The original price may include ordering, handling, installation, or other work that remains. Calculate the credit for costs and work actually removed, using the pricing basis in your agreement. State which charges remain.
If the customer supplies a mirror and the agreed credit is $260, describe the removed work accurately. Do not say installation is removed if you still have to install the supplied item. Record any limits on inspecting or handling customer-supplied products in the contract and change order.
Keep deductive changes in the same numbering sequence as additions. The record and final invoice will then reconcile both.
How do you bill change orders on progress and final invoices?
Bill approved changes as distinct lines, with the change order number, description, and amount. On a progress invoice, state whether you are billing the full approved change or only its completed portion. Do not bill the same change again on the final invoice.
Use the payment timing in your agreement or approved change. If the billing plan changes, record it. See contractor payment schedules for the broader plan, and the construction invoice and estimate app page for estimates, invoices and payment tracking.
For this bathroom job, the original contract is $14,200. CO #1 adds $553 for the subfloor repair. CO #2 deducts $260 because the customer supplies the mirror. The revised contract is $14,200 + $553 - $260 = $14,493. After a $4,000 deposit and a $5,000 progress payment, the balance is $14,493 - $4,000 - $5,000 = $5,493.
| Final invoice line | Amount |
|---|---|
| Original contract | $14,200 |
| CO #1, replace 32 sq ft of rotten subfloor | +$553 |
| CO #2, customer supplies mirror | -$260 |
| Revised contract total | $14,493 |
| Less deposit received | -$4,000 |
| Less progress payment received | -$5,000 |
| Balance due | $5,493 |
Check the invoice against the change log and payment records. If you exchange a lien waiver for each payment, list any approved but unpaid change orders on it so you do not waive them by accident. Separate approved changes from unfinished work on the punch list.
What if the customer will not sign?
Do not perform non-urgent extra work on the assumption that the customer will pay later. Explain the condition, price, and schedule effect, then ask what the customer wants to do. If the customer declines, record the decision and continue only with unaffected work in the agreement.
If a change is needed to protect property or address a safety concern, take reasonable steps within your role, record the condition and actions, and contact the customer promptly. An emergency does not by itself give you the right to bill for the work, so get the customer’s written go-ahead as soon as you can reach them.
When a customer disputes the price, explain the quantities and assumptions. Offer a revised scope only if you can perform it safely and stand behind it. Keep the original proposal and any revision; do not erase the first version.
If the customer asks you to proceed without signing, reply in writing that the work is on hold until the contract’s approval method is met. Record who gave the instruction and when. Review estimates that win the job to make future scopes and exclusions clear.
What changes are common by trade?
Describe the site condition, quantity, pricing unit or rate, and what could trigger another change. These are pricing approaches, not market rates; use your own costs and contract terms.
| Trade | Common change | How to price it |
|---|---|---|
| Roofing | Rotten decking found after shingles are removed | Price per sheet replaced, with removal, new decking, fastening, disposal, and any related material stated. |
| Electrical | Panel or circuit found not to code during the planned work | Describe the observed issue and proposed correction; price labor, parts, access, and any inspection or coordination work that applies. |
| Plumbing | Corroded valve or galvanized line exposed | State the section or fixture included, access and restoration limits, parts, labor, and what happens if corrosion extends farther. |
| Painting | Extra coats required after a color change | Price the additional preparation and coats by the affected area or agreed labor basis; record the selected color and finish. |
| Flooring | Subfloor needs leveling before installation | Measure the affected area and price leveling per sq ft, stating the preparation and product included. |
| Handyman | Customer adds tasks while you are on site | List each task and its materials, then price labor per hour or by task under the agreed rate and minimums. |
Avoid a catch-all line such as “extra repairs” when you can name the task and quantity. If you cannot measure a hidden condition until opening more of the assembly, define and get approval for the first portion, then get another approval before expanding the work.
FAQ
Can I write a change order after the extra work is done?
You can document what happened, but a later form does not replace approval before extra work. Send the customer photos, scope, price, and timeline, and ask for a written decision. Record when the work happened and when the customer responded.
Can a change order increase the project schedule?
Yes, if the change affects the work plan, access, materials, or sequence. State the expected added time or why timing is uncertain before approval. Update the customer if a new discovery changes the estimate.
Should I charge a markup on change order materials?
Use the pricing method in your agreement and explain the amount or basis. In the bathroom example, a 20% markup on $140 of materials is $28, making the materials charge $168. Do not call markup margin.
What should a change order text message say?
Identify the job and change order number, describe the work, state the price or credit, and note the schedule impact. Ask for clear written approval and save the full exchange. Follow the approval method in your contract.
How do I handle a change that I cannot price yet?
Explain what you found and why you cannot see the full extent. Propose a defined next step with a stated price or pricing method, then get approval before proceeding. Pause for another change order if opening the assembly reveals more work.