Free estimate template

Construction estimate template

A construction estimate should break the project into a schedule of values, so each progress draw ties to a defined phase of work. It should also show retainage and explain how priced change orders will be added after approval.

What belongs on an estimate for construction work

  • Project address, building type, and the areas included in the construction scope
  • Schedule of values for phases such as site work, foundation, framing, and rough-ins
  • Mobilization and site setup costs for equipment, layout, and temporary protection
  • Separate labor, material, equipment, and subcontractor allowances where needed
  • Retainage percentage and how it will be withheld from progress draws
  • Written exclusions and a process for pricing and approving change orders

How construction work is priced

Construction estimates may use measured units such as cubic yards of concrete, square feet of framing, or linear feet of pipe, alongside lump sums for mobilization, permits, or a defined work package. Break the contract value into schedule of values phases, then tie each progress draw to a completed milestone or measured work. Price added scope as a separate change order once its labor, materials, and schedule effect are clear.

Tax, deposits and terms

Show labor and materials separately when the project's tax rules or owner reporting call for it. Tax treatment varies by state and project type, so confirm which lines are taxable before finalizing the estimate. State the deposit amount or calculation, when progress draws are due, how retainage is withheld, and when the final balance is due; tie draws to named construction milestones and say whether the deposit is credited to the contract total.

A worked example

Illustrative schedule of values for a detached garage through framing.

Line itemQtyUnitWhy it is billed that way
Mobilization and site setup, $2,0001jobCovers one setup for the garage work area and equipment.
Excavate and grade garage pad, $3,0001lotBilled as a defined site work package.
Concrete slab, $6,00012cubic yardsQuantity is tied to the concrete placed for the slab.
Frame walls and roof, $17,0001,100sq ftMeasured area supports the framing phase value.
Retainage held from approved progress draws, $2,80010%of drawShown as withheld from the example completed work, not as a discount.

Three mistakes on construction estimates

Vague progress milestones

A draw listed only as "next phase" does not tell the owner what work earns it. Name the construction milestone, such as foundation complete or framing inspection passed, and state what completion means.

Retainage treated as a discount

Showing retainage as a price reduction makes the contract value look lower than it is. List it as an amount withheld from progress draws and state when the held amount becomes due.

Unpriced scope changes

A revised wall layout or added opening can change framing labor, materials, and the schedule. Price that added work in a written change order and get approval before including it in a draw.

Construction estimate questions

How do I set up a schedule of values for a construction estimate?

Break the contract scope into priced phases that match how the job will be built, such as site work, foundation, framing, and mechanical rough-ins. Give each phase a value and use the same phase names on progress billing. Keep allowances and work not yet defined separate.

Should retainage appear on a construction estimate?

Yes, show the retainage percentage and explain how it will be withheld from progress draws. State when the withheld amount is due, such as after the listed closeout work is complete. Check the contract and applicable rules for the project.

How do I price a change order on a construction job?

Describe the added or revised work, then price its labor, materials, equipment, and any subcontractor work. Note any effect on the schedule of values or completion date. Get written approval before adding the change order to a progress draw.

Or skip the template

Invocket numbers the document, remembers the customer, renders the PDF on the phone and tracks whether it was paid, offline, with no account. The template is here for the jobs where a one-off file is genuinely faster.

Bill the job before you leave the driveway

No account to create, nothing to set up. Open the app and write the first estimate.

Get Invocket for iPhone