What does preliminary notice mean?

An early notice to the property owner that you are supplying labor or materials to their project.

On this page

In practice

Often called a notice to owner. In many states it is a precondition for filing a mechanic’s lien later, with a hard deadline counted from your first day on the job. It is a routine administrative step, not an accusation, sending it on every job is the safe habit.

What is a preliminary notice?

A preliminary notice, also called a notice to owner, is a written notice that tells the property owner and other project parties you are furnishing labor or materials. On some jobs, sending it on time is a step toward protecting your right to make a mechanics' lien claim if you are not paid.

It is not the lien itself or a demand for immediate payment. It alerts project parties early. The name, recipients, delivery rules, and effect vary by state, so check the rules where the project is located.

Do not confuse it with a mechanic's lien. The notice can be an earlier requirement; the lien is a separate step with its own rules and deadline.

Who sends a preliminary notice on a construction job?

Subcontractors and suppliers are common senders, especially when they are not hired directly by the owner. A general contractor may also have notice duties in some places. Who must send one depends on your role, project type, and state law. Do not assume the owner or general contractor will handle it for you.

If you are a subcontractor, identify who hired you and who is above that party in the payment chain. Confirm the required recipients and delivery method for your state. Keep a dated copy and proof of delivery.

The notice identifies your work or materials and tells project parties you are involved. If your scope changes, check whether your state requires an updated notice.

What should a notice to owner include?

Use the form and instructions for the project state. Gather the information needed to identify the job and your contribution. Depending on the state's requirements, the notice may ask for:

  • Your business name and contact information.
  • The owner's name and project address or description.
  • The general contractor or hiring party.
  • A description of your labor or materials and when you started.
  • The notice date and required delivery information.

This is a preparation list, not a universal legal checklist. Confirm the current form, recipients, delivery method, and proof of service rules. Keep the notice with your contract, invoices, and any lien waiver documents. A waiver and notice serve different purposes, so read each before signing or sending it.

When is a 20 day preliminary notice due?

There is no single nationwide deadline. California's Civil Code uses a 20-day preliminary notice under section 8204. Subcontractors and suppliers in particular send it to protect lien rights. Do not apply that timeline to a project in another state.

For Texas residential projects, Property Code section 53.056 requires a subcontractor to send notice to the owner and original contractor by the 15th day of the second month after the month labor or materials were provided. Commercial deadlines differ. For example, materials provided in April put that stated Texas residential deadline on June 15.

Other deadlines may apply too. California Civil Code section 8412 says a direct contractor must record a lien within 90 days after completion of the work of improvement, or within 60 days after the owner records a notice of completion or cessation, whichever is earlier. Check your state statute and project type before calculating dates.

Record when you started work or supplied materials, the recipients, the deadline, and delivery proof. If payment is late, a notice does not replace invoices or later deadlines. See the guide to handling late payments.

Preliminary notice examples by state. Check requirements for your project.
StateWho sends itDeadlineSource
CaliforniaSubcontractors and suppliers in particular20-day preliminary noticeCivil Code section 8204
Texas residentialSubcontractorBy the 15th day of the second month after the month labor or materials were providedProperty Code section 53.056
Your stateCheck your state's requirementsCheck the state statute, county recorder or a construction lawyerCheck the state statute, county recorder or a construction lawyer

Questions

Do I need to send a preliminary notice?

It depends on your state, project type, and role in the payment chain. Subcontractors and suppliers often need to pay close attention to notice rules, but requirements are not the same everywhere. Check the state statute and project instructions, or ask a construction lawyer before a deadline passes.

Is a preliminary notice the same as a notice to owner?

The terms can refer to an early project notice, but names and legal requirements vary by state. The document may have specific recipients and delivery rules where the project is located. Check the terminology in your state's statute or form instead of relying on a notice labeled for another state.

Does a preliminary notice guarantee I will get paid?

No. A notice is not payment, a lien, or a guarantee that a customer will pay. Where required, timely notice may help preserve a step in your lien rights, but other rules and deadlines can apply. Keep your contract, invoices, delivery records, and payment follow-ups, and check your state's requirements.

What if I miss the preliminary notice deadline?

The result depends on the law and facts for the project state, so do not assume it is the same everywhere. Check the statute promptly and speak with a construction lawyer about your options. Keep proof of when you started work or supplied materials and exactly what notice you sent.

About this page

Invocket Editorial

Written by the team that builds Invocket, an invoicing app for contractors. We check prices and rules against published sources, name them on the page, and update the page when they change. How we write and check these pages.

Keep going

Bill the job before you leave the driveway

No account to create, nothing to set up. Open the app and write the first estimate.

Get Invocket for iPhone